How to make a construction schedule
A good construction schedule does three jobs: it tells everyone what happens next, who does it, and what slips if something runs late. You don't need expensive software or a scheduling consultant to get there. Here's the process, start to finish.

1. Break the job into phases
Start with the big pieces in the order they happen: preconstruction (permits, submittals, long-lead orders), sitework, foundations, structure, rough-in, close-in, finishes, inspections and closeout. On a remodel the phases are smaller, but the order still matters.
2. List the activities under each phase
Write each activity as something one crew finishes: "Frame second floor walls", not "Framing". Aim for activities of a few days to two or three weeks. Anything longer usually hides work you'll want to track separately.
3. Give each activity a duration in working days
Use your own crews' numbers where you have them. Where you don't, start from typical production rates and adjust. Count working days, not calendar days, and decide up front whether any trade works six-day weeks.
4. Link the activities
This is the step most schedules skip, and it's the one that makes them useful. For each activity, ask "what has to be done before this can start?" Drywall can't start until rough inspections pass; countertops can't be templated until cabinets are set. Once activities are linked, moving one date moves everything that depends on it.
5. Find the critical path
The critical path is the chain of linked activities with no slack: if any of them slips a day, the finish date slips a day. Those are the activities to watch every week. Everything else has some room.
6. Assign a responsible party to every activity
Every line needs an owner: your crew, a named sub, the owner or the architect. A schedule without names is a wish list.
7. Set the start date and calendar
Put in the real start date (notice to proceed or permit issued) and the holidays your crews take. Then save a copy of the dates as your baseline, so later you can see what moved and why.
8. Update it every week
Mark progress, move what slipped, and log why (weather, a late inspection, a resubmittal). Then print a two- to three-week look-ahead for the field. That's the part most crews actually use day to day; see how to run a 3-week look-ahead.