The 3-week look-ahead schedule, and how to run one

A 3-week look-ahead is a short-range schedule that shows only the next two to six weeks of work, in day-by-day detail, so the field knows exactly what's coming and what has to be ready for it. The master schedule tells you when the job finishes. The look-ahead tells your superintendent and subs what happens Monday.

A printed 3-week look-ahead from LookAhead, grouped by subcontractor, with an open roadblock listed below
A 3-week look-ahead printed from LookAhead: grouped by sub, with open roadblocks and need-by dates.

Why three weeks

Three weeks is long enough to order materials, line up inspections and confirm crews, and short enough that the dates are still believable. Some teams run two weeks on small jobs and four to six on large ones. The routine is the same.

What goes on it

The weekly routine

  1. Update the master schedule. Mark what got done, move what slipped, and note why.
  2. Pull the next three weeks. Everything in the window, grouped by trade so each sub sees their own work together.
  3. Walk it with the team. In the weekly meeting, go line by line: "Is this still happening? What do you need?"
  4. Log the roadblocks. Anything that could stop work gets an owner and a need-by date.
  5. Print it and post it. In the trailer, in the job box, and sent to each sub.

Common mistakes

New to scheduling? Start with how to make a construction schedule.