A ground-floor room addition or a second story, tied into the existing house. Answer a few questions about your project and LookAhead builds the whole schedule, with tasks linked, trades assigned and durations sized to your job.

Use this template free
Opens in your browser. No account needed to start; a free account saves up to 3 schedules.
29linked activities at the example size
3.3 monthsto substantial completion at the example size
11trades and parties assigned

What’s in the schedule

  • Preconstruction
  • Foundation & structure
  • Rough-in & finishes
  • Inspections & closeout
  • Milestones

Questions it asks

  • Addition type
  • Addition size (sq ft)
  • Includes a bathroom
  • Project name and construction start date

Durations, crew sequencing and the number of floors, buildings or rooms adjust to your answers.

Example size

The numbers above are for this example. Yours change with your answers.

Addition type: Ground floor (new foundation)Addition size (sq ft): 500Includes a bathroom: yes

Trades included

General contractorConcreteFramingMEP (mech / elec / plumbing)Insulation & drywallWindows & exteriorRoofingInterior finishesOwner / tenantTile & stoneInspector / agency

How it works

1. Answer the questions

Size, floors, units or scope. It takes about a minute.

2. Review and adjust

Every task is linked, so change one date and the rest follows. Edit anything to match your crews.

3. Print or share

Print a clean schedule or a 2–6 week look-ahead for the field, or send a view-only link to subs and owners.

Durations are planning-level starting points based on typical industry production rates. Review them against your own crews, market and design.

Get the whole schedule in about 10 minutes. Free for up to 3 schedules at a time.

Use this template free

More residential templates

Production home (tract) constructionA subdivision of single-family homes: land development, then homes built in releases.
Custom home constructionOne custom or semi-custom home, from permit to move-in — slab, crawlspace or basement.
Kitchen remodelFrom a cosmetic refresh to a full gut — cabinet lead time drives when demo starts.